Claim · 2024-11-01 · publication · Stated in source · Supported

FERC, by order issued on 1 November 2024 (189 FERC ¶ 61,078, Docket ER24-2172), rejected the amended Interconnection Service Agreement among PJM, Susquehanna Nuclear and PPL Electric Utilities, which would have increased the co-located load at the Susquehanna plant from 300 MW to 480 MW. World Nuclear News reported the rejection on 4 November 2024.

One recorded claim. The claim panel gives its qualification, the source passages with their place in each source, and how it was checked.

What it connects

→ recorded a regulator decision on → Rejection of the amended Susquehanna Interconnection Service Agreement (co-located load 300 MW to 480 MW)