Records found and checked by machines, not reviewed by an editor · What this means →

Claim · 2025-06-20 · effective · Stated in source · Supported

Texas S.B. 6 adds Utilities Code Section 37.0561, under which the commission's large-load interconnection standards for the ERCOT region apply to new or expanded interconnections above a demand threshold, set at 75 MW unless the commission finds a lower threshold necessary.

One recorded claim. The claim panel gives its qualification, the source passages with their place in each source, and how it was checked.

What it connects

Texas S.B. 6 (89th Legislature): planning for, interconnection and operation of, and costs of serving certain electrical loads → states provision → Utilities Code Sec. 37.0561(c): large-load interconnection standards apply above a 75 MW threshold unless the commission sets a lower one

Where it appears

No collection page holds this claim. It is listed with its records in the explorer.