Section 2(a) of Executive Order 14318 defines a "Data Center Project" as a facility requiring more than 100 MW of new load dedicated to AI inference, training, simulation or synthetic data generation. Copy claim link
Copy claim reference
Machine-checked, not reviewed by an editor Stated in source Supported
Supporting evidence: primary · 1 source; Context: primary · 1 source
Provision Threshold or trigger · provision ID us-eo14318-sec2a Subject version As published in the Federal Register (28 July 2025) · Published 2025-07-28 · Effective date not established Date 2025-07-28 · publication Figure measures facility power Quantity more than · 100 megawatts (MW) of new load Scope and limits A definition for the order's purposes. Qualifying Projects (Sec. 2(d)) also include Data Center or Covered Component Projects with at least $500 million in committed capital expenditure, an incremental electric load addition above 100 MW, projects that protect national security, or designation by the Secretary of Defense, the Interior, Commerce or Energy.
The evidence 02 primary source Supports the claim
Executive Order 14318: Accelerating Federal Permitting of Data Center Infrastructure (90 FR 35385) ↗ Federal Register (Office of the Federal Register, National Archives) via govinfo.gov · 2025-07-28
Copy source reference
Cite the original source Cite the original document, not Selekoa. Check these details against it.
Copy APA
Download BibTeX Download RIS Download CSL-JSON
Source excerpt “means a facility that requires greater than 100 megawatts (MW) of new load dedicated to AI inference, training, simulation, or synthetic data generation” Location in source Sec. 2(a), 90 FR 35385
How it was read Retrieved directly from the publisher
Machine-checked · 2026-10-30
Source details and check notes Authors The White House Version Retrieved for the candidate pack on 2026-10-28 (SHA-256 c478f9300bab5533400ddfaf4b5853748eed773effcbc3484cf7595c53fdbd1a). Federal Register print of 28 July 2025, Vol. 90, No. 142, pp. 35385 ff., FR Doc. 2025-14212. Retrieved again at admission on 2026-10-30 (SHA-256 c478f9300bab5533400ddfaf4b5853748eed773effcbc3484cf7595c53fdbd1a, the same bytes). Canonical address Open the canonical source ↗ Accessed 2026-10-28 Language English (en) Attribution The White House, “Executive Order 14318: Accelerating Federal Permitting of Data Center Infrastructure (90 FR 35385)”, 2025-07-28. Reuse No open redistribution licence asserted. Bibliographic metadata, editorial paraphrases and short attributed quotations (at most 50 words each). Recheck terms before wider redistribution. Check notes Candidate pack passage, compute, power and orbit (research/compute-power-orbit). The quotation (23 words) matched the text retrieved for the candidate pack on 2026-10-28 and again at admission on 2026-10-30, in a fresh retrieval whose SHA-256 equals the pack’s. Matching ignored differences of whitespace, case, quotation marks, dashes and Unicode compatibility forms, so the source’s typography can differ. A cross-family machine check (2026-10-29/30, item 51) re-read the record’s sources and found full support. No human editorial review. primary source Context only
Executive Order 14318: Accelerating Federal Permitting of Data Center Infrastructure (90 FR 35385) ↗ Federal Register (Office of the Federal Register, National Archives) via govinfo.gov · 2025-07-28
Copy source reference
Cite the original source Cite the original document, not Selekoa. Check these details against it.
Copy APA
Download BibTeX Download RIS Download CSL-JSON
Paraphrase a "Qualifying Project" is a Data Center Project or Covered Component Project (i) with at least $500 million in committed capital expenditures, (ii) involving an incremental electric load addition of greater than 100 MW, (iii) that protects national security, or (iv) otherwise designated by the Secretary of Defense, the Interior, Commerce or Energy.
Location in source Sec. 2(d), 90 FR 35385–35386
How it was read Retrieved directly from the publisher
Machine-checked · 2026-10-30
Source details and check notes Authors The White House Version Retrieved for the candidate pack on 2026-10-28 (SHA-256 c478f9300bab5533400ddfaf4b5853748eed773effcbc3484cf7595c53fdbd1a). Federal Register print of 28 July 2025, Vol. 90, No. 142, pp. 35385 ff., FR Doc. 2025-14212. Retrieved again at admission on 2026-10-30 (SHA-256 c478f9300bab5533400ddfaf4b5853748eed773effcbc3484cf7595c53fdbd1a, the same bytes). Canonical address Open the canonical source ↗ Accessed 2026-10-28 Language English (en) Attribution The White House, “Executive Order 14318: Accelerating Federal Permitting of Data Center Infrastructure (90 FR 35385)”, 2025-07-28. Reuse No open redistribution licence asserted. Bibliographic metadata, editorial paraphrases and short attributed quotations (at most 50 words each). Recheck terms before wider redistribution. Check notes Candidate pack passage, compute, power and orbit (research/compute-power-orbit). The paraphrase is Selekoa’s, written from the text retrieved for the candidate pack on 2026-10-28; it is not a quotation and was not machine-matched. The cross-family check found it faithful. A cross-family machine check (2026-10-29/30, item 51) re-read the record’s sources and found full support. No human editorial review. Status and meaning Editorial status. Not reviewed by an editor . An exploratory record that no editor has accepted. This status does not say whether a person has read any linked passage. Each evidence record above shows how it was checked.
Relation. An exact framework edition, or another document with an exact expression, states one provision: a capability threshold or risk level and its trigger, a required safeguard or action, a decision authority (who decides, recommends, can overrule or is informed), a stated exception, or another statement of its content, such as a licence term or a prospectus statement. The passage records what the document says, not implementation, compliance or effectiveness. Provisions with the same key align across editions of one family.
Date. Provision as the text states it, dated by its date of publication, 2025-07-28. Signed on 23 July 2025; published in the Federal Register of 28 July 2025.