Institutional dossier
The documented history of HUMAIN: chronology, people, research, capital and compute, and governance. Every statement opens its source and its limits.
Records dated 2025-05-13 to 2025-05-13 · 0 undated
2 claims · 2 sources · 2 not editorially accepted. The counts describe this selection. They do not measure completeness or independent confirmation.
Scope, evidence and limits
Description: Saudi AI company described by AMD as “Saudi Arabia’s new AI enterprise”; ownership is not recorded from the retrieved texts.
The records are grouped automatically. No human inspection of the selected claims, source paths or framing is recorded for this dossier. Each source passage shows how it was checked.
The dossier is computed from existing records. It is not a continuous history of the institution, and a missing record does not mean that an event or relationship did not happen. The chronology uses the dates of events and reports, not the date the public could first have known of them. Later sources can describe earlier events.
Select any statement to see its exact claim, qualification, date note, evidence passage, location in the source, source version and review status. The description above is Selekoa’s stored description of the institution, based on these sources:
Chronology
Records about the institution itself and documented changes to its frameworks, by year. Expand a year to read the claims. People’s other institutional records and related documents have their own sections. Where a date gives only the year or month, the order within it is unknown.
2025Record year · 2 claims
- AMD and HUMAIN announced on 13 May 2025 an agreement under which the parties will invest up to $10 billion to deploy 500 megawatts of AI compute capacity over five years, with HUMAIN delivering the data-centre, power and fibre infrastructure and AMD providing its AI compute portfolio and ROCm software.HUMAIN → has a supply agreement with → Advanced Micro Devices, Inc. (AMD)Inspect claim & evidence ↗
Record about this institution · Stated in source · Supported
Stage: announced · up to USD 10,000,000,000 · programme · exact 500 MW (as worded: '500 megawatts of AI compute capacity'; the subheading says 'up to 500 megawatts of AI infrastructure')
Qualification and date notes
The $10 billion is stated for "the parties" together and is not attributed to either. A five-year plan; AMD also states that initial deployments are underway and that the collaboration is on track for multi-exaflop capacity by early 2026, which is a target, not a result.
Date of the announcement, as the source gives it.
- HUMAIN and NVIDIA announced on 13 May 2025, in a release on NVIDIA's newsroom, that HUMAIN was making an investment to build AI factories in Saudi Arabia with a projected capacity of up to 500 megawatts powered by several hundred thousand NVIDIA GPUs over five years, the first phase being an 18,000-chip NVIDIA GB300 Grace Blackwell AI supercomputer.HUMAIN → has a supply agreement with → NVIDIAInspect claim & evidence ↗
Record about this institution · Stated in source · Supported
Stage: announced · up to 500 MW (as worded: 'projected capacity of up to 500 megawatts')
Qualification and date notes
A projected capacity over five years and an announced first phase; it does not show GPUs shipped, an export licence granted, or a contract price. "Several hundred thousand" is the release’s wording, not a count.
Date of the announcement, as the source gives it.