Institutional dossier
The documented history of Vistra: chronology, people, research, capital and compute, and governance. Every statement opens its source and its limits.
Records dated 2026-01-09 to 2026-01-09 · 0 undated
1 claims · 1 sources · 1 not editorially accepted. The counts describe this selection. They do not measure completeness or independent confirmation.
Scope, evidence and limits
Description: Owner of the Perry, Davis-Besse and Beaver Valley nuclear plants.
The records are grouped automatically. No human inspection of the selected claims, source paths or framing is recorded for this dossier. Each source passage shows how it was checked.
The dossier is computed from existing records. It is not a continuous history of the institution, and a missing record does not mean that an event or relationship did not happen. The chronology uses the dates of events and reports, not the date the public could first have known of them. Later sources can describe earlier events.
Select any statement to see its exact claim, qualification, date note, evidence passage, location in the source, source version and review status. The description above is Selekoa’s stored description of the institution, based on these sources:
Chronology
Records about the institution itself and documented changes to its frameworks, by year. Expand a year to read the claims. People’s other institutional records and related documents have their own sections. Where a date gives only the year or month, the order within it is unknown.
2026Record year · 1 claims
- Meta announced on 9 January 2026 20-year nuclear energy agreements to purchase more than 2.1 GW from Vistra's Perry and Davis-Besse plants in Ohio and energy from uprates at those plants and Beaver Valley in Pennsylvania, the uprates totalling 433 MW expected in the early 2030s.Meta → has a power agreement with → VistraInspect claim & evidence ↗
Record about this institution · Stated in source · Supported
Stage: contracted · more than 2.1 GW of energy (as worded: 'more than 2.1 GW'), plus uprates totalling 433 MW
Qualification and date notes
Meta's account; contract terms are not published. The uprates are planned. Meta states the projects deliver power to the grids supporting its operations, including the Prometheus supercluster in New Albany, Ohio; this is not a direct supply to that site.
Stated by Meta; Vistra's release was not retrieved.